Stable layer solidification of municipal road subgrade

It can replace the traditional cement to stabilize the gravel layer, reduce the cost and shorten the construction period.

路基施工

Engineering background

A new municipal road project with a total length of 10 kilometers. The original design of the pavement base layer used cement-stabilized gravel, but due to the shortage of local gravel resources and high prices, the budget was seriously overrun. At the same time, the construction schedule is tight and there is an urgent need to find alternatives.

technological innovation

After expert argumentation, it was decided to use "modified lime powder as roadbed supplement" combined with plain soil for solidification treatment as the pavement base.
Process flow: plain soil paving -> spreading curing agent -> rotary tiller mixing -> roller compaction -> maintenance.

Economic benefits

After adopting soil solidification technology, the excavation soil of the roadbed is directly used, saving a lot of gravel material costs and transportation costs. According to statistics, the roadbed construction cost of this project was reduced by about 25%, and the construction speed was increased by 30%, and it was completed and opened to traffic one month ahead of schedule.

project files

Project type municipal road
construction time 2021
Application products Modified lime powder
cost saving about 25%